Gemini 1 was the first mission in NASA's Gemini program.[2] An uncrewed test flight of the Gemini spacecraft, its main objectives were to test the structural integrity of the new spacecraft and modified Titan II launch vehicle. It was also the first test of the new tracking and communication systems for the Gemini program and provided training for the ground support crews for the first crewed missions.[3]
![]() Launch of Gemini 1 | |
Mission type | Test flight |
---|---|
Operator | NASA |
COSPAR ID | 1964-018A ![]() |
SATCAT no. | 782 |
Mission duration | 4 hours 50 minutes |
Distance travelled | 1,733,541 miles (2,789,864 km) |
Orbits completed | 63 |
Spacecraft properties | |
Spacecraft | Gemini SC1 |
Manufacturer | McDonnell |
Launch mass | 7,026 pounds (3,187 kg) (11,400 pounds (5,170 kg) with 2nd stage) |
Start of mission | |
Launch date | April 8, 1964, 16:01:01.69 (1964-04-08UTC16:01:01Z) UTC |
Rocket | Titan II GLV, s/n 62-12556 |
Launch site | Cape Kennedy LC-19 |
End of mission | |
Disposal | Uncontrolled reentry |
Decay date | April 12, 1964, 15:00:00 (1964-04-12UTC16Z) UTC |
Landing site | Middle of South Atlantic Ocean |
Orbital parameters | |
Reference system | Geocentric |
Regime | Low Earth orbit |
Perigee altitude | 84 nautical miles (155 km) |
Apogee altitude | 146 nautical miles (271 km) |
Inclination | 32.5 degrees |
Period | 88.76 minutes |
Epoch | April 10, 1964[1] |
Project Gemini Gemini 2 → |
Originally scheduled for launch in December 1963, difficulties in the development of both the spacecraft and its booster caused four months of delay. Gemini 1 was launched from Launch Complex 19 at Cape Kennedy (now Canaveral), Florida on April 8, 1964. The spacecraft stayed attached to the second stage of the rocket. The mission lasted for three orbits while test data were taken, but the spacecraft stayed in space for almost 64 orbits until its orbit decayed due to atmospheric drag. The spacecraft was not intended to be recovered, and holes were drilled through its heat shield to ensure it would not survive re-entry.
Project Gemini was conceived as a bridge between America's single-seat Project Mercury and the three-seat Project Apollo. With a design largely extrapolated from its predecessor,[4]: 71 the Gemini spacecraft would allow two astronauts to conduct the maneuvers inherent in Apollo's lunar mission: rendezvous, docking, and changing of orbit. Moreover, Gemini would support astronauts in space for extended flights, approximating the expected length of the Apollo missions.[4]: 55–74
Its two-person capacity and greater capabilities meant that Gemini would be a substantially heavier spacecraft than Mercury had been — too heavy to be lofted into orbit by Mercury's Atlas rocket. A replacement was needed. The newly developed Titan II ICBM (which had also been tapped by the Air Force for its X-20 spaceplane project) was an attractive replacement. It had a thrust some two and a half times that of the Atlas, a far simpler mechanical construction, and the ability to store propellants indefinitely. Moreover, the Titan II's propellants mixed less violently than those of Atlas meaning a booster explosion, should it happen, would be less violent. This made obsolete the heavy escape tower used in the Mercury program; instead, ejection seats could be used.[4]: 41–42
The primary goal of the first Gemini mission was to flight test the modified Titan II launch vehicle and the basic structural soundness of the Gemini capsule under launch and orbital conditions. Consequently, the first Gemini capsule could be a largely boilerplate structure.[4]: 181 Secondary goals of the mission included testing the remote guidance systems, the Titan's redundancy systems, and evaluation of the Gemini-Titan malfunction detection system.[5]
Gemini Spacecraft Number 1 was built specifically for the uncrewed mission. Most internal systems were replaced with dummies and ballast approximating the weight and balance of the crewed spacecraft. In place of the crew couches, two pallets of instruments were installed for the relaying via telemetry of the pressure, vibration, acceleration, temperature, and structural loads experienced during the short flight. A spacecraft heat shield was installed, but four large holes were drilled in it to ensure Gemini 1 was destroyed during reentry.[4]: 181
Even with the simplified systems, this first Gemini encountered several weeks of delay in testing. Nevertheless, it was not the spacecraft that caused the launch date, originally planned for December 1963, to slip. Rather, it was the testing and man-rating of the Titan II launch vehicle. Assembled on May 21, 1963, the first Titan-Gemini launch vehicle required comprehensive testing and retesting, and it was not until October that it was ready for transport to the launch site — where considerable preparation still had to be done.[4]: 185 Moreover, there was concern that the Titan II produced too much vertical oscillation (pogo) to be usable at all, and consideration was given to using the Saturn I rocket instead, at least for the first missions. However, on November 1, 1963, the Air Force flew a Titan II rocket with standpipes in its oxidizer lines and mechanical accumulators in its fuel lines, which suppressed the pogo effect.[6]
Inefficient project management threatened to further delay the first Gemini launch, which by November had already been pushed back to February 28, 1964. Gemini Manager Charles Mathews united the several disparate teams into a single Gemini Launch Vehicle Coordination Committee with clearly defined management and communication channels.[4]: 188 This measure ensured that no more time would be lost due to uncertain authority, duplicated effort, or conflicting decisions. Still, issues that arose during testing caused the launch date to slip further.[4]: 189 The Titan II booster was not ready for final readiness testing until March 3, 1964, the same day that Gemini Spacecraft Number 1 arrived at the launch complex for mating with its booster.[4]: 190 Faulty test equipment caused a further delay of two weeks. By late March, all serious hurdles cleared, Gemini 1's launch date was set for April 7.[4]: 195 The resolution of a failure in the secondary autopilot caused one last day of delay. Finally, by noon of the seventh, Gemini 1's Mission Review Board determined unanimously that all systems were cleared for flight.[4]: 197
After a flawless countdown, Gemini 1's Titan II booster lifted off from Cape Kennedy's (now Canaveral) Launch Complex 19[4]: 194 at 11:00:01 EDT, April 8, 1964.[4]: 197 The first stage was jettisoned after two and a half minutes with the rocket 35 nautical miles (64 km) high and 49 nautical miles (91 km) downrange. At that moment, there was an unexpected three-second loss of signal from the craft. It was later determined that this brief communications blackout was caused by charged ions from the separation and startup of the second stage, similar to the blackout during spacecraft reentry. All subsequent Gemini flights would have the same brief blackout.[7]
The spacecraft achieved orbit five and a half minutes after launch. The launch vehicle had imparted an excess 7 meters (24 feet) per second of velocity to the Gemini 1, placing the spacecraft into an orbit with an apogee of 170 nautical miles (320 km) instead of the planned 161 nautical miles (299 km). This lengthened Gemini 1's lifespan from the planned three and a half days to four.[4]: 199
The formal mission of Gemini 1 was over long before that. Its battery had only been designed to last a single orbit,[8] and only the first three orbits — lasting four hours and 50 minutes — were part of the flight plan. Gemini 1 and its attached second stage were tracked by the Manned Space Flight Network until they reentered over the South Atlantic, midway between South America and Africa, on April 12, 1964, during their 64th orbit.[4]: 199
As a result of the successful flight, the Titan II was considered "man-rated" (safe for use in human spaceflight).[4]: 200 Man-rating the Gemini capsule itself would not be accomplished until the launch of Gemini 2 nine months later, on January 19, 1965.[4]: 209
The Gemini 1 mission was supported by 5,176 United States Department of Defense personnel, as well as eleven aircraft and three ships provided by the Department of Defense.[4]: Appendix G-299
This article incorporates public domain material from websites or documents of the National Aeronautics and Space Administration.
Project Gemini | ||||||
---|---|---|---|---|---|---|
Missions |
| ![]() | ||||
Astronauts |
| |||||
Components |
| |||||
Launch sites |
| |||||
Developments |
| |||||
Related |
|
NASA | |||||||
---|---|---|---|---|---|---|---|
Policy and history |
| ||||||
Human spaceflight programs |
| ||||||
Robotic programs |
| ||||||
Individual featured missions (human and robotic) |
| ||||||
Communications and navigation |
| ||||||
NASA lists |
| ||||||
NASA images and artwork |
| ||||||
Related |
| ||||||
|
← 1963 · Orbital launches in 1964 · 1965 → | |
---|---|
Poppy 3 · GGSE-1 · SOLRAD 7A · SECOR 1 | OPS 3367A · OPS 3367B | Relay 2 | Echo 2 | Jupiter Nosecone | Elektron 1 · Elektron 2 | Ranger 6 | OPS 3444 | Zond 3MV-1 No.2 | Kosmos 25 | OPS 2423 | OPS 3722 | OPS 3435 | Kosmos 26 | BE-A | Luna E-6 No.6 | OPS 3467 | Kosmos 27 | Ariel 2 | Zond 1 | Kosmos 28 | Gemini 1 | Polyot 2 | Luna E-6 No.5 | Transit 5BN-3 · Transit 5E-4 | OPS 3743 | Kosmos 29 | OPS 2921 | Kosmos 30 | OPS 3592 | Apollo AS-101 | OPS 4412 | OPS 3483 | Molniya-1 No.2 | Kosmos 31 | Kosmos 32 | OPS 3236 | OPS 4467A · OPS 4467B | OPS 3754 | Kosmos 33 | ESRS | Atlas-Centaur 3 | Kosmos 34 | OPS 3395 | OPS 3684 · OPS 4923 | Elektron 3 · Elektron 4 | OPS 3491 | Kosmos 35 | Vela 2A · Vela 2B · ERS-13 | Ranger 7 | Kosmos 36 | OPS 3042 | Kosmos 37 | OPS 3802 · OPS 3216 | Kosmos 38 · Kosmos 39 · Kosmos 40 | Syncom 3 | OPS 2739 | Kosmos 41 | Kosmos 42 · Kosmos 43 | Kosmos 44 | Titan 3A-2 | OGO-1 | Kosmos 45 | OPS 3497 | Apollo AS-102 | OPS 4262 | Kosmos 46 | Explorer 21 | OPS 3333 | Kosmos 47 | OPS 5798 · Dragsphere 1 · Dragsphere 2 | OPS 4036 | Explorer 22 | Voskhod 1 | Kosmos 48 | OPS 3559 | Strela-1 No.6 · Strela-1 No.7 · Strela-1 No.8 | OPS 4384 · OPS 5063 | Kosmos 49 | Kosmos 50 | OPS 5434 | OPS 3062 | Mariner 3 | Explorer 23 | OPS 3360 | Explorer 24 · Explorer 25 | Mariner 4 | Zond 2 | DS-2 No.2 | OPS 4439 | Kosmos 51 | Titan 3A-1 | Surveyor Mass Model | OPS 6582 · Transit 5E-5 | San Marco 1 | OPS 3358 | Explorer 26 | OPS 3762 | |
Payloads are separated by bullets ( · ), launches by pipes ( | ). Crewed flights are indicated in underline. Uncatalogued launch failures are listed in italics. Payloads deployed from other spacecraft are denoted in brackets. |